A pump sized by the calculation, not by fear.

Fire Pumps: Supply, Installation and Commissioning in Egypt

Electric, diesel and jockey sets with controllers and valves, sized to your required flow and pressure.

Request a quote on WhatsApp (opens WhatsApp in a new tab) Estimate the pump size

We reply during working hours: Saturday–Thursday 8 am–6 pm

  • 137 documented projects since 2010
  • All governorates of Egypt
  • 137 documented projects
  • 17 governorates with documented projects
  • 16 years in fire protection
  • 48 working hours to review your BOQ

Clients from our work register

Fire pumps in Egypt, installed by HTC: a split-case fire pump and its discharge line with a check valve and a padlocked valve.

Which size do you need: a 250, 500 or 750 gpm fire pump?

Enter the hazard and the number of standpipes: the calculator works out the demand, then the size to NFPA 20, step by step.

Hazard OH12 standpipesSprinklered throughoutHeight 20 m

Occupancy hazard (NFPA 13)

Light hazard: Offices, classrooms, hospitals

Ordinary hazard, group 1: Car parks, bakeries, laundries

Ordinary hazard, group 2: Light manufacturing, low-pile storage warehouses, workshops

Extra hazard, group 1: Printing plants, sawmills

Extra hazard, group 2: Flammable liquid spraying or flow coating, foam plastics manufacturing

0 if the building has no standpipe system.

Is the building sprinklered throughout?
In metres
Does the facility have any of the following?

Preliminary result

Worked example — change the inputs and press Calculate

Smallest acceptable size under NFPA 20
750gpm
750 × 1.5 = 1125 ≥ 752.89
Typical size
1,000gpm
Smallest NFPA 20 standard size of at least 752.89 gpm
Smallest acceptable size under NFPA 20: 750 gpm covers the demand within 150% of its rated flow (up to 1,125 gpm), where NFPA 20 still requires at least 65% of the rated pressure. It is acceptable only when the pump curve confirms the required pressure at that point and the churn stays within the system pressure limits; the typical 1,000 gpm size meets the demand at 100% of its flow.
Design demand
752.9gpm
Jockey pump — rule of thumb
10.0gpm
Water tank — shorter duration
115.5m³
30,525 gal · 60 min
Pressure required at the pump (approx.)
10.6bar
(153.4 psi)
  • Standpipe demand: the Egyptian code (305) part 4, clause 2‑6‑8‑1 governs — 2,850 L/min (752.9 gpm); NFPA 14: 750 gpm.
  • Residual pressure at the most remote outlet: NFPA 14 governs as the stricter — 6.9 bar (100 psi); the Egyptian code (305) part 4, clause 2‑6‑6‑2: 4.5 bar (65.3 psi).
  • Water tank: the NFPA volume governs — 115.5 m³; the Egyptian code (305) part 1, clause 3‑10‑5‑11: at least 90 m³.
Calculation steps and assumptions
Calculation steps and assumptions
Item Formula Value
Sprinkler demand 0.15 × 1500 × 1.15 258.8 gpm
Hose stream allowance From the occupancy hazard OH1 250 gpm
Standpipe demand, NFPA 14 NFPA 14: min(500 + 250 × (2 − 1), 1000) 750 gpm
Standpipe demand, Egyptian code Egyptian code (305), part 4, clause 2‑6‑8‑1: min(1900 + 950 × 1, 3800) = 2850 L/min 752.9 gpm
Governing standpipe demand The larger of the two: max(750, 752.89) 752.9 gpm
Design demand max(508.75, 752.9) 752.9 gpm
Smallest acceptable size under NFPA 20 Smallest NFPA 20 standard size that meets the demand at 150% of its flow: 750 × 1.5 = 1125 ≥ 752.89 750 gpm
Typical size Smallest NFPA 20 standard size that meets the demand at 100% of its flow: 1000 ≥ 752.89 1,000 gpm
Jockey pump — rule of thumb max(1, 0.01 × 1000) 10.0 gpm
Supply duration From the occupancy hazard OH1: 60–90 min 60 min
Wet‑riser reserve, Egyptian code Egyptian code (305), part 1, clause 3‑10‑5‑11: 60 + 30 × 1 90 m³
Tank volume — shorter duration max(508.75 × 60, 752.89 × 30, 90 ÷ 0.003785) 30,525 gal
Tank volume — shorter duration 30525 × 0.003785 115.5 m³
Tank volume — if the AHJ requires the longer duration max(508.75 × 90, 752.89 × 30, 90 ÷ 0.003785) 45,788 gal
Tank volume — if the AHJ requires the longer duration 45788 × 0.003785 173.3 m³
Governing residual pressure at the most remote outlet The larger of NFPA 14 and the Egyptian code (305), part 4, clause 2‑6‑6‑2: max(100 psi, 4.5 bar = 65.3 psi) 100.0 psi
Pressure required at the pump (approx.) 100 + 20 × 1.42 + 25 153.4 psi
Pressure required at the pump, in bar 153.4 ÷ 14.504 10.6 bar

Assumptions

Hydraulic imbalance allowance
1.15 ×
Friction and fittings allowance
1.7 bar (25 psi)
Static head per metre
0.098 bar/m (1.42 psi/m)

Preliminary constants used by this calculator; the hydraulic calculation replaces them in the final design.

Where the standpipe values come from — NFPA 14 (2019)

  • §7.10.1.1.1 At least 500 gpm for the hydraulically most remote standpipe.
  • §7.10.1.1.3 250 gpm for each additional standpipe, in buildings with floor areas that do not exceed 7432 m² per floor.
  • §7.8.1 A residual pressure of at least 6.9 bar (100 psi) at the most remote 2½ in. hose connection.

Egyptian Code for Fire Protection of Buildings (305)

  • part 4, 2-6-8-1 At least 1900 L/min for the hydraulically most remote standpipe and 950 L/min for each additional one, with a system total of at most 4750 L/min (floor area up to 7500 m²).
  • part 4, 2-6-8-3 In a building sprinklered throughout with a combined system, the standpipe demand need not exceed 3800 L/min unless the authority requires more.
  • part 4, 2-6-6-2 A residual pressure of at least 4.5 bar at the hydraulically most remote hose connection.
  • part 4, 2-6-7-1 At most 12 bar residual at hose connections larger than 38 mm; above it, a listed pressure‑regulating device.
  • part 1, 3-10-5-11 A wet‑riser reserve of at least 60 m³ for the first riser and 30 m³ for each other riser.

The calculator takes the larger of the Egyptian code value and the NFPA value for each item.

Preliminary estimate — to be checked against the code in force and approved by a qualified engineer.

Ask the assistant about a code clause

Answers from the Egyptian code and NFPA text with the clause, and says so when the text has no answer.

Ask the assistant about a code clause

0 / 1,200

Enter to send · Shift + Enter for a new line

Suggested questions

Automated assistant — guidance only; the authority having jurisdiction decides

Fire pumps: supply and installation, electric, diesel and jockey

  • Main fire pump (electric or diesel)
  • Jockey pump
  • Controllers
  • Valves, flow meter and test header
  • Diesel fuel tank and engine exhaust
  • Performance test at 0%, 100% and 150% of rated flow
  • Handover documents
to systemfrom tank123456789101112131415to systemfrom tank123456789101112131415

Fire pump room: electric main pump and jockey pump Illustration, not to scale · Dashed line: pressure‑sensing line

Drawing key
  1. 1 Main fire pump, horizontal split‑case
  2. 2 Electric motor (driver)
  3. 3 Jockey pump, vertical in‑line
  4. 4 Main fire pump controller
  5. 5 Jockey pump controller
  6. 6 Suction from the tank, OS&Y gate valve
  7. 7 Eccentric reducer at the suction flange, flat side up
  8. 8 Main relief valve to an open waste cone, where NFPA 20 requires it
  9. 9 Circulation relief valve, to drain
  10. 10 Discharge check valve
  11. 11 Pressure‑sensing line, one per controller, tapped between the check valve and the discharge control valve
  12. 12 Discharge control valve, OS&Y
  13. 13 Discharge header to the system
  14. 14 Test line: normally closed valve and flow meter
  15. 15 Test header with hose valves, outside the room

Built first, promised second

The red discharge header of an outdoor pump house: risers with check valves and gate valves, a vertical jockey pump and two controllers.
A diesel-engine-driven split-case fire pump on a concrete plinth, with its fuel tank alongside.
A vertical jockey pump between red risers and valves, with the pump controllers behind it.

Work completed by HTC Fire Protection

Documented projects

From HTC's project register: 137 documented projects since 2010

  • UTOPIA Pharma, 10th of Ramadan City Sharqia Fire pumps 2022
  • Sea Grain, El Dekheila port Alexandria Fire pumps, Fire fighting, Fire alarm, Gas suppression 2021
  • Danone factory, El Obour Qalyubia Fire pumps, Maintenance 2021
  • Hilton Taba Resort, dive centre South Sinai Fire pumps, Fire fighting 2014
More documented projects (2) (4)
  • Danone factory, El Obour Qalyubia Fire pumps, Maintenance 2021
  • Hilton Taba Resort, dive centre South Sinai Fire pumps, Fire fighting 2014
  • Heart Academy Hospital, Abbassia Cairo Fire pumps, Fire fighting 2016
  • Zahran Mall, Mansoura Dakahlia Fire pumps, Fire fighting, Gas suppression, Maintenance 2020

We work in every governorate of Egypt

Shaded governorates are where we have documented projects

Documented projects by governorate
GovernorateProjects
Cairo 42
Alexandria 10
Giza 7
Qalyubia 5
Sharqia 5
Ismailia 4
Suez 3
Red Sea 2
Beheira 2
Dakahlia 2
South Sinai 2
Matrouh 2
Port Said 2
Aswan 1
Gharbia 1
Minya 1
Monufia 1

Clients include

  • EGOTH
  • Cairo Airport Passenger Services
  • Hilton Taba
  • Knauf
  • Danone
  • Pharma Swede
  • UTOPIA PHARMA
  • Zahran
  • Idra Power
  • Titan
  • Heart Academy Hospital
  • Sea Grain

From site visit to commissioning and acceptance testing

  1. Site survey
  2. Design and calculation
  3. Supply
  4. Installation
  5. Testing, commissioning and handover
  6. Periodic maintenance

Value engineering: the same protection, for less where the code allows

We size the pump to the calculated demand and its operating point on the manufacturer's curve instead of oversizing it, and check the choice against the Egyptian Code for Fire Protection of Buildings (305).

The usual solution

A pump sized with a safety margin.

Ours, by the code

Sized to the hydraulically calculated demand, with the pressure checked on the manufacturer's curve at the operating point, at 150% of rated flow and at churn, and a listed pressure‑regulating device where the residual pressure at a hose connection exceeds 12 bar.

Basis Clause 2‑6‑7‑1 of part 4 of the Egyptian code

To be checked against the code in force and approved by a qualified engineer.

Fire pump prices for contractors

Contractor pricing against the same BOQ items, with the handover documents.

48 working hours Free review of a BOQ or a quotation you received — technical notes and saving opportunities, no obligation.

What you get back from the review:

  • What complies Items that meet the project and the code, left as they are.
  • What exceeds the requirement What can be removed or downsized without a breach: the saving.
  • What is missing What could fail the inspection if it stays missing.
  • Which quantities need checking Quantities we ask you to check against the drawings.

Common questions before signing

What do fire pumps cost in Egypt, and what drives the price?

The flow rating alone does not set the price; the driver, the required pressure, UL/FM listing and whether the set includes the jockey pump, valves and fittings do.

We select the standard size that meets the flow and the pressure together. Size the pump above, or send the flow and pressure in bar for a written quotation.

Estimate the pump size

We are a contractor: do you price at contractor rates?

Yes, against the same BOQ items: supply, installation and testing at contractor rates, with the handover documents.

We return your BOQ with technical notes and saving opportunities within 48 working hours, free of charge.

Upload a BOQ file (opens WhatsApp in a new tab)

Will the fire pump pass the Civil Protection inspection?

The decision belongs to the Civil Protection authority, not to us or any contractor, so we do not promise it.

What we commit to: a pump to the Egyptian code and NFPA 20, a performance test at 0%, 100% and 150% of rated flow, and handover documents.

Do fire pumps in Egypt need UL listing or FM approval?

NFPA 20 requires a pump and controller listed for fire service; the usual listings are UL and FM. The listing approves the equipment, not the contractor.

We supply what the project and the authority require, no more, and state the listing in the quotation.

Request a quote on WhatsApp (opens WhatsApp in a new tab)

What are the fire pump room requirements?

A dedicated room separated by fire‑rated construction or in a separate building, easy to reach, with drainage, lighting, ventilation and heat that prevents freezing.

A diesel pump also needs a fuel tank, an exhaust to the outside and two battery sets with a charger; the authority sets the separation rating.

Fire pump room checklist (Arabic)

How long do supply and installation take?

It depends on the pump, the driver, the listing required and availability, so we do not quote a general figure.

We state the time and stages in writing in the quotation after the site visit, and agree any shutdown with you first.

Do you offer maintenance contracts for pump rooms?

Yes, to NFPA 25: pump runs, the annual performance test and valve inspection, with a technical report after every visit.

The fire pump room checklist (Arabic) is free to print.

Request a fire pump quote

A ready WhatsApp message, or a three‑step form.

Or fill in the request form

Service and governorate

Three short steps: service and governorate, then facility and file, then your contact details.

Facility and file
Facility type

BOQ or drawing: send it in the WhatsApp chat after you send the request.

Contact details

Egyptian mobile, 11 digits starting with 01